2019–2022 | Preparation
03.2022 | Constitutive meeting of the Evaluation Committee
05.2022 | Approval of the project + brief by the Prague City Council
05.2022 | Approval of the project + brief by the Prague City Assembly
05.2022 | Opening the Competitive Dialogue Procurement Procedure
03.06.2022 | Publication of the Contracting Authority’s Profile
07.2022 | Request to participate
08.2022 | elaboration of the access methodology
09.2022 | evaluation of access methodology / selection of 5 team
10-12.2022 | elaboration of the design concept
12.2022 | Evaluation of concepts / selection of 3 teams
12.2022-03.2023 | proposal work
03.2023 | proposal introduction
05.-09.2023 | drafting of the proposal (in progress)
10.2023 | evaluation of tenders + refined proposals
11.2023 | announcement of the results of the Competitive Dialogue
12.2023 | signing of contracts with the selected contractor
¾ 2024 | refinement of the study
2026 | expected start of implementation
A detailed timetable is specified in the Tender Documentation.